MONTRA continues the collaboration initiated with SIEMENS PP&AL in this case in a mechanical installation Project.
The scope of MONTRA mainly includes the mechanical installation of approximately 1.9kms of baggaging conveyors. The works are developed over 5 months in 6 clearly differentiated phases / zones and two main levels.